Dr Sim: non performing contractor will be terminated
Sarawak Local government and Housing Minister, Datuk Dr Sim Kui Hian warned that he will terminate contract with the contractor for drainage upgrading system project at Jalan Batu Kawa Lorong 3 if the contractor does not commence the project within this week.
He lamented that the contractor has been given many opportunity to complete the project, yet still unable to meet the government’s requirement.
The project of upgrading the earth drain to concrete drain is under DID department. It was approved on 2017 October and expected to be completed 2018 March.
However, the contractor failed to deliver. DID department had issued a Certificate of Non Compliance and warning letter on April and June 2018 respectively.
« Joy of sharing Sarawak Independence Day (Previous News)
(Next News) Tiang: do not be colonised by Malaya »
Related News
Sebastian Ting calls to public to donate blood to save lives
Members of the public are encouraged to make blood donation a regular habit to helpRead More
Sebastian Ting assists family in obtaining Malaysian citizenship after three-year wait
Piasau assemblyman Datuk Sebastian Ting has assisted a family in Miri to resolve their citizenshipRead More



Comments are Closed