The RM7.77 million second-phase flood mitigation project at Gem Park is expected to reduce flood risks in the area and benefit approximately 500 residents.
The project, implemented by the Sarawak Department of Irrigation and Drainage (DID), will take 18 months to complete. Construction is scheduled to begin on November 23, 2026, and is expected to be completed by May 22, 2028.
Deputy Premier Datuk Amar Dr Sim Kui Hian said the project design takes into account Gem Park’s low-lying terrain and the need for its drainage system to accommodate surface runoff from surrounding areas.
He said a main drainage channel would direct rainwater from neighbouring areas into the river, while a retention pond would be constructed to temporarily hold excess water when river levels rise.
“Once the river level recedes, pumps will be used to discharge the accumulated water to prevent it from remaining in the residential area,” he said.
According to TVS, Dr Sim was speaking to reporters after attending the groundbreaking ceremony for the Gem Park flood mitigation project yesterday.
The project will cover 94 houses and involve the construction of two reinforced concrete drains measuring 558 metres and 265 metres in length, with widths of five metres and one metre respectively.
Other works include raising the existing earth bund to 3.6 metres and elevating the road level to 3.1 metres.
Dr Sim said the project was among five local flood mitigation initiatives currently being implemented in Bintulu. One has been completed, while another has reached 86 per cent progress.
However, he noted that flooding in Bintulu was also influenced by water flowing from upstream areas and changes in sea levels, making more comprehensive and large-scale flood mitigation measures necessary.
He added that the Sarawak and Federal governments must work together in planning and providing funding to effectively address Bintulu’s flooding problems.