LO CLARIFIES ON UPGRADING AND WIDENING OF THE ROADS ALONG JALAN BAU, JALAN BATU KITANG AND JALAN STEPHEN YONG
English Nov 13, 2026 • 3:35 AM
Admin 12 Readers
Batu Kitang assemblyman Dato Ir Lo Khere Chiang clarified the confusion arising from contradictory reports in the press and television news regarding the proposed commencement dates of 2027 and 2028 for the upgrading and widening of the road from Bau to Keranji.
He said this clarification is also intended to address certain misconceptions arising from questions posed to me during my visit to Telaga Air on 8 October 2026.
"First and foremost, I wish to assure the public that the proposed upgrading and widening of Jalan Bau, Jalan Batu Kitang and Jalan Stephen Yong into a four-lane carriageway is a genuine and important infrastructure project. It involves three constituencies, namely Batu Kitang, Serembu and Bau.
Discussions and consultations involving the relevant stakeholders, the Public Works Department (JKR), engineering consultants and local communities have been ongoing. Given the scale, complexity and financial implications of this project, careful planning and coordination are essential to ensure its successful implementation, " he said in a press conference today.
According to him the proposed project will be undertaken in three phases.
Phase 1: Bau to Keranji involves the upgrading and widening of the road from Bau to Keranji into a four-lane carriageway, at an estimated cost of RM500 million.
This phase, he added is currently at the design stage. Subject to the completion of the necessary planning, approval and funding processes, the tender exercise, contract award and commencement of construction may take place in 2028.
He emphasised that 2028 is a projected timeline and not a confirmed commencement date.
Phase 2: Keranji to Jalan Stephen Yong involves the upgrading and widening of the road from Keranji to Jalan Stephen Yong, including the construction of an additional two-lane bridge alongside the existing Batu Kitang Bridge.
The estimated cost of this phase is also RM500 million.
Upon completion of Phases 1 and 2, Lo added that motorists travelling from Bau through Keranji and Jalan Stephen Yong towards Kuching will benefit from a safer, smoother and more convenient four-lane road connection which will significantly improve traffic flow, reduce congestion and enhance road safety for the thousands of motorists who depend on this important route daily.
For Phase 3, he said it is along Jalan Stephen Yong to 7th Mile and involved the upgrading and widening of the remaining stretch of road between Jalan Stephen Yong and the 7th Mile traffic lights.
This section, he stated presents considerable engineering and logistical challenges due to the presence of major water pumping mains, SESCO electrical cables and telecommunications infrastructure, particularly along the stretch between the 7th Mile traffic lights and the Jalan Stephen Yong/Bumbok junction.
Lo said ut is therefore more practical to proceed with Phase 3 after the completion of Phases 1 and 2 and by then, motorists travelling between Bau and Kuching will have an improved alternative route through Keranji and Jalan Stephen Yong, allowing Phase 3 construction works to proceed with minimal interference to traffic flow.
The project he added is a major Infrastructure Investment Exceeding RM1.5 Billion and a project of this magnitude cannot be implemented hastily. It requires comprehensive engineering studies, detailed designs, proper financial planning, utility coordination and phased construction to ensure public funds are utilised responsibly and effectively.
He urged the people understand the frustration and inconvenience experienced by motorists who use this stretch of road daily, particularly during peak hours.
The concerns expressed by the rakyat are genuine, and I share their desire to see this long-awaited road improvement project implemented as soon as possible.
Nevertheless, I appeal to the people of N13 Batu Kitang, as well as all residents and motorists who regularly travel along this route, to remain patient and understanding.
I sincerely hope that the GPS caretaker government will be given the opportunity to make the necessary financial allocations and implement this important project progressively, according to a carefully planned and practical schedule.
Our priority must be to ensure that this project is not only started, but successfully completed in a responsible, systematic and sustainable manner.
The upgrading of this vital road corridor is an investment in better connectivity, improved road safety, reduced traffic congestion and the future development of our communities.
I remain committed to pursuing this project and working with all relevant parties to see it through to completion.
Let us work together with patience, understanding and determination to achieve a safer and better road network for the benefit of all.