Sebastian Ting Inspects Upgrading Works at Kampung Pulau Melayu Multi-Purpose Hall
English Jul 29, 2026 • 1:33 PM
English News or Articles 9 Readers
Sarawak Deputy Minister for Tourism, Datuk Sebastian Ting Chiew Yew, inspected the RM200,000 upgrading project at the Kampung Pulau Melayu Multi-Purpose Hall and discovered several areas leaking.
He immediately sought explanations from the contractor and officers from the Miri Public Works Department (JKR), and instructed the contractor to thoroughly inspect and rectify the issues.
He said the inspection coincided with heavy rain, which exposed several defects.
The roof of the existing hall was suspected to be leaking due to ageing and deterioration, while the newly extended section was found to have inadequately connected roof canopies.
In addition, some windows lacked proper rain protection, allowing rainwater to enter the hall.
The upgrading project was funded under the 2025 Rural Transformation Programme (RTP) with an allocation of RM200,000. Construction began on Jan 6 this year and was originally scheduled for completion on July 5, but the contractor completed the project ahead of schedule on June 19.
The contractor explained that the leaking roof belonged to the original structure, which was not included in the scope of the upgrading works. As the hall had been in use for many years, the roof may have deteriorated over time, resulting in water seepage during prolonged heavy rain and leaving water stains inside the building.
Although the affected roof section was outside the project scope, Ting instructed the contractor to assist in identifying the source of the leak and carry out the necessary repairs to prevent future disruption to the hall's use.
He also pointed out that the newly completed upgrading works still required improvements. These included uneven wall paint, generally poor finishing work, and insufficient rain protection above some of the newly installed windows. During heavy rain accompanied by strong winds, rainwater could be blown directly into the hall through these windows.
Ting added that the connection between the newly constructed roof canopy and the existing building was found to be poorly sealed, leaving gaps that allowed rainwater to seep into the hall during the morning downpour.
He instructed the contractor to conduct a comprehensive inspection of all the identified issues, including the roof canopy connections, rain protection for the windows and the overall quality of the finishing works, and to carry out rectification work as soon as possible.
He said that although the project had been completed ahead of schedule, it was still covered by a one-year defects liability period. Therefore, the contractor remained responsible for repairing all defects identified during the inspection, while the relevant authorities would continue monitoring the rectification process to ensure all issues were properly resolved.