SEBASTIAN TING SAYS MIRI DRAINAGE UPGRADING PROJECTS PROGRESSING, MORE AREAS TO BENEFIT FROM RTP FUNDS
English Nov 05, 2026 • 3:42 PM
Admin 14 Readers
Several drainage upgrading projects in Piasau are progressing, with efforts continuing to address ageing drainage infrastructure and reduce the risk of flash floods in residential areas.
Piasau assemblyman Datuk Sebastian Ting said several projects were being implemented to improve drainage conditions, including two projects funded under the Rural Transformation Programme (RTP).
One of the projects, costing RM150,000 under RTP 2025, involves upgrading and improving existing reinforced concrete drains along Jalan Lautan 1 and Jalan Lautan 4 in Ocean Park.
The three-month project, undertaken by Canaan Enterprise, was handed over on Sept 21, 2026, with completion scheduled for Dec 20, 2026.
According to the project report, the scope covers 122 metres of drainage works, including upgrading of culverts. As of Nov 4, physical progress stood at 35 per cent against the planned 50 per cent.
Ting said the project had experienced a slight delay but efforts were being made to speed up the work.
Another project, costing RM7,000, involves 76 metres of drainage work and is scheduled for completion on Jan 1, 2027. He said it was slightly behind schedule, by about three per cent, but the contractor was making efforts to complete the work.
Meanwhile, a separate RM100,000 project under RTP 2026 involves upgrading and improving existing reinforced concrete drains along Jalan Lautan 1 and Jalan Lautan 4 in Ocean Park, Miri.
The three-month contract was handed over on Oct 22, 2026, with completion scheduled for Jan 21, 2027. As of Nov 4, physical progress stood at five per cent against the planned eight per cent.
Ting said upgrading ageing drainage infrastructure had been among his priorities over the past decade, particularly in areas where residents frequently faced drainage problems whenever heavy rain occurred.
He said conditions in many locations had improved significantly following drainage upgrading works, although one or two areas still required attention.
He added that some projects had taken longer to implement because of land-related issues, requiring discussions and cooperation from landowners before the necessary work could proceed.
On flash floods in Miri city centre, Ting said he would engage residents and the relevant authorities to work towards a comprehensive drainage master plan.
He said the plan should adopt a long-term approach, with implementation mapped out over five, 10 and 15 years to address the city's drainage needs systematically.
"Whenever it rains, residents feel uncomfortable. Some cannot even sleep peacefully because they are worried about flooding," he said.
Ting said discussions with the relevant parties would be important in identifying practical solutions and ensuring that drainage improvements could be carried out in stages.